华星东方承建的河北省邢台沙河海创生活垃圾焚烧发电项目烟气净化工程于2021年6月19日通过72+24小时试运行。
The flue gas cleaning (FGC) project constructed by Huaxing East for Shahe, Xingtai municipal waste incineration plant in Hebei province passed 72+24 hours trial operation on June 19, 2021.
该项目处理规模一期为2×500t/d垃圾焚烧炉生产线,预留二期,终期2000t/d。烟气处理采用SNCR+旋转喷雾半干法+干法喷射+活性炭吸附+袋式除尘器+1#GGH+湿法脱酸+2#GGH+SGH+SCR+飞灰输送、储存及稳定化工艺,为我司EP工程。
Phase I of the plant has 2 × 500 t/d waste incineration lines. Phase II is reserved, and the full capacity is 2000 t/d. The FGC adopts SNCR + rotary spray semi-dry method + dry injection + active carbon adsorption + bag filter + #1 GGH + wet de-acid + #2 GGH + SGH + SCR + fly ash conveying, storage and stabilization process. It is an EP project of Huaxing.
华星东方在河北省的业绩涵盖包括:唐山、沧州、衡水、曹妃甸、围场、保定一期、二期、顺平、唐山一期、二期、张家口北、固安、香河、定州、沧州一期、石家庄、安平、三河等多个项目。
Huaxing East's achievements in HeBeiProvince include: Tangshan,Cangzhou,Hengshui,Caofeidian,Weichang,Baodingphase i,Baodingphase ii,Shunping,Tangshanphase i,Tangshanphase ii,Zhangjiakou north,GuAn,Xianghe,Dingzhou,Cangzhouphasei,Shijiazhuang,Anping,Sanhe etc.
评论